Constructive acceleration
This concept is not (currently) a recognised concept under English law.
Constructive acceleration is acceleration of the construction works following failure by the employer to recognise that the contractor has encountered employer delay for which the contractor is entitled to an extension of time and which failure required the contractor to accelerate its progress in order to complete the works by the contract completion date.
This situation may be brought about by the employer’s denial of a valid request for an extension of time or by the employer’s late granting of an extension of time.
For more information see: https://www.scl.org.uk/resources/delay-disruption-protocol
[edit] Related articles on Designing Buildings Wiki
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Your guide to The Construction Reset at UKCW Birmingham.
Accommodating the Victorian and Edwardian working woman. Book review.
Rethinking passive fire protection in design
PFP demands the same level of design rigour as structure or services.
38% of Gen Zs feel safe when a fire door is wedged open.
Stunning images from around the world
Shortlist for CIOB’s Art of Building photography competition.
Guidance for conversion of traditional pre-1919 stone buildings.
Industrial heritage in the Ruhr
A marked difference to the fate of industrial landscapes in the UK.
Communities will be able to build their own clean energy.
Why diversity and inclusion matters for SMEs
CIOB’s D&I Charter shows how practical changes can support long-term growth.
Cut electricity bills to power growth
Coalition sends joint letter to the Chancellor.
Gasholders: a history in pictures. Book review.
Recognition, influence and growth
SocEnv identifies three strategic pillars in new strategy to 2045.